For 2008:

LIBRARY RENOVATION $6,500,000

LUCAS RENOV & CHERRY ENGINEERING LABORATORY $6,800,000

MUSIC BLDG RENOVATION & ADDITION $2,000,000

NEW SOCCER FIELD $1,000,000

For 2009:

CARDINAL STADIUM RENOVATION $6,500,000

HIGGINS FIELDHOUSE REPLACEMENT $5,000,000

MUSIC BLDG RENOVATION & ADDITION $4,400,000

NEW ADMINISTRATIVE SERVICES BLDG (Renov Brooks/Shivers) $3,000,000

NEW FIELDHOUSE for SOCCER, SOFTBALL, BASEBALL $3,500,000

SYNTHETIC TURF $950,000

For 2010:

CARDINAL VILLAGE V $19,200,000

NEW ADMINISTRATIVE SERVICES BLDG (Renov Brooks/Shivers) $4,000,000

NEW SOFTBALL FIELD $1,200,000

For 2011:

BIOLOGY BUILDING $12,400,000

HEALTH & HUMAN PERF COMPLEX A RENOVATION $2,600,000

REPLACE FACILITIES MANAGEMENT COMPLEX $10,900,000

Plus other projects in 2012 and 2013, including a $20 Million research bldg and a $18 Million performing arts center.

Guest coachacola
Posted

According to the board of regents meeting in August, here's the projects happening at LU right now:

I. Project Planning & Programming

1) Cardinal Stadium Renovation & Higgins Fieldhouse Replacement

Programmer: Leo A. Daly Est. Cost: $18,633,294

Architect: Leo A. Daly Est. Completion: October 2009

Design work is currently underway and CM@Risk proposals are being solicited.

2) Music Building Project

Architect: VLK Est. Cost: $ 7,423,000

Programmer: Broaddus & Associates Est. Completion: August 2009

Programming is 100% complete. The design architect has been selected and proposals are being solicited for the CM@Risk.

II. Design/Construction Document Phase

3) Cherry Engineering Building Addition

Architect: VLK Architects, Inc. Est. Cost: $7,829,000

Contractor: SeTEX Construction Corp. (CM@R) Est. Completion: July 15, 2009

The Construction Manager-at-Risk and the architect are working on developing the GMP for the project.

III. Construction Phase

4) Repairs to Football Press Box

Architect: Leo A. Daly Est. Cost: $1,504,000

Contractor: N&T Construction, Inc. Completion: May 1, 2008

The project is about 95% completed with a few items remaining. The seats in the press box are to be installed outside of the general contractor’s responsibility.

5) Roof Replacement – eleven buildings

Engineer: AmTech Roofing Consultants Est. Cost: $2,661,612

Contractors: Various Est. Completion: Various

The Board of Regents delegated the Chancellor authority to enter into a contract with AmTech Roofing Consultants to design roof replacements for Brooks/Shivers Hall , Administrative Services), Setzer, Mamie McFadden, Geology, Social & Behavioral Sciences, North Central Plant, Women’s Gym A-Health & Human Performance ,Hayes Biology, Art Building #4, and Energy Management Buildings. Various contractors were engaged for these roofs. All buildings are now complete. Some final reports have already been submitted, with the remainder pending.

Guest abovetherim
Posted

Thanks for the update coachacola and great question UNLV. I was starting to wonder about some of this myself.

  • Member Statistics

    47,047
    Total Members
    1,837
    Most Online
    LPfam
    Newest Member
    LPfam
    Joined
×
×
  • Create New...